I-15 North Phase 3 Speedway to Garnet Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Virtual Public Information Meeting

The Nevada Department of Transportation held a virtual public information meeting on the upcoming construction of I-15 N Phase 3 Speedway Blvd to Garnet Interchange. To learn more about the meeting, visit www.I-15North.com.

Project Overview

This is the final phase of improvements to the I-15 North Corridor Environmental Assessment. The original project limits were from the Speedway Boulevard Interchange to the Apex Interchange. Following a 2007 environmental assessment, the project limits were extended 6.1 miles north of Apex to the Garnet Interchange (US 93).

A 10.7-mile stretch of I-15 will be widened from four lanes to six lanes (first construction package). The second construction package includes a new weigh station, enforcement improvements, truck parking and an interchange between Speedway and Apex. I-15 North Project Area Map

Project Benefits

  • Improve safety
  • Improve travel time reliability
  • Improve access to planned developments in North Las Vegas
  • Improve operations

Project Costs

  • Engineering: $3.4 - $4.9 million 
  • Right-of-Way: $0.1 - 0.2 million
  • Construction: $89.2 - $92 million

Timeline

  • Planning: Completed
  • Environmental Phase: 2019-2021
  • Final Design: 2020-2021 (First Construction Package)
  • Construction: 2022-2025 (First Construction Package)

Contact

Project Manager
Dwayne Wilkinson 