The Nevada Department of Transportation held a virtual public information meeting on the upcoming construction of I-15 N Phase 3 Speedway Blvd to Garnet Interchange. To learn more about the meeting, visit www.I-15North.com.
Project Overview
This is the final phase of improvements to the I-15 North Corridor Environmental Assessment. The original project limits were from the Speedway Boulevard Interchange to the Apex Interchange. Following a 2007 environmental assessment, the project limits were extended 6.1 miles north of Apex to the Garnet Interchange (US 93).
A 10.7-mile stretch of I-15 will be widened from four lanes to six lanes (first construction package). The second construction package includes a new weigh station, enforcement improvements, truck parking and an interchange between Speedway and Apex.
Project Benefits
- Improve safety
- Improve travel time reliability
- Improve access to planned developments in North Las Vegas
- Improve operations
Project Costs
- Engineering: $3.4 - $4.9 million
- Right-of-Way: $0.1 - 0.2 million
- Construction: $89.2 - $92 million
Timeline
- Planning: Completed
- Environmental Phase: 2019-2021
- Final Design: 2020-2021 (First Construction Package)
- Construction: 2022-2025 (First Construction Package)