Nevada Department of Transportation
Home MenuDocuments
- NDOT_Map_Index2
- NDOT_Map_Index
- Quad 0101
- Quad 0102
- Quad 0103
- Quad 0104
- Quad 0105
- Quad 0106
- Quad 0107
- Quad 0108
- Quad 0109
- Quad 0110
- Quad 0111
- Quad 0112
- Quad 0201
- Quad 0202
- Quad 0203
- Quad 0204
- Quad 0205
- Quad 0206
- Quad 0207
- Quad 0208
- Quad 0209
- Quad 0210
- Quad 0211
- Quad 0212
- Quad 0301
- Quad 0302
- Quad 0303
- Quad 0304
- Quad 0305
- Quad 0306
- Quad 0307
- Quad 0308
- Quad 0309
- Quad 0310
- Quad 0311
- Quad 0312
- Quad 0401
- Quad 0402
- Quad 0403
- Quad 0404
- Quad 0405
- Quad 0406
- Quad 0407
- Quad 0408
- Quad 0409
- Quad 0410
- Quad 0411
- Quad 0412
- Quad 0501
- Quad 0502
- Quad 0503
- Quad 0504
- Quad 0505
- Quad 0506
- Quad 0507
- Quad 0508
- Quad 0509
- Quad 0510
- Quad 0511
- Quad 0512
- Quad 0601
- Quad 0602
- Quad 0603
- Quad 0604
- Quad 0605
- Quad 0606
- Quad 0607
- Quad 0608
- Quad 0609
- Quad 0610
- Quad 0611
- Quad 0612
- Quad 0701
- Quad 0702
- Quad 0703
- Quad 0704
- Quad 0705
- Quad 0706
- Quad 0707
- Quad 0708
- Quad 0709
- Quad 0710
- Quad 0711
- Quad 0712
- Quad 0801
- Quad 0802
- Quad 0803
- Quad 0804
- Quad 0805
- Quad 0806
- Quad 0807
- Quad 0808
- Quad 0809
- Quad 0810
- Quad 0811
- Quad 0901
- Quad 0902
- Quad 0903
- Quad 0904
- Quad 0905
- Quad 0906
- Quad 0907
- Quad 0908
- Quad 0909
- Quad 1001
- Quad 1002
- Quad 1003
- Quad 1004
- Quad 1005
- Quad 1006
- Quad 1007
- Quad 1008
- Quad 1101
- Quad 1102
- Quad 1103
- Quad 1104
- Quad 1105
- Quad 1106
- Quad 1107
- Quad 1201
- Quad 1202
- Quad 1203
- Quad 1204
- Quad 1205
- Quad 1302
- Quad 1303
- Quad 1304
- Quad 1402
- Quad 1403
I-15 South Project: Sloan Road to North of Warm Springs Road
Construction underway through December 2025
Project Overview
The Nevada Department of Transportation (NDOT) began improvements along nearly nine miles of Interstate 15 (I-15) South from Sloan Road to north of Warm Springs Road in January 2024. This Project will aid in improving travel-time reliability, serve proposed growth in the area by increasing local mobility and access, and enhance I-15’s operational efficiency. Construction is anticipated to be completed within a 24-month period.
Project features include:
- Widening I-15 from six to eight general-purpose lanes between Sloan Road and St. Rose Parkway
- Widening and restriping I-15 from six to 10 general-purpose lanes between St. Rose Parkway and Blue Diamond Road
- Adding a High Occupancy Vehicle (HOV) lane in each direction between St. Rose Parkway and Blue Diamond Road
- Resurfacing bridges and pavement preservation at the Blue Diamond Interchange
- Construction of 6 new sound walls near qualifying residential areas throughout the corridor
Project Cost and Funding
The total cost for construction is $86 M. The project is paid for with 95% federal and 5% state funds. Funding sources include National Highway Performance Program (NHPP), Surface Transportation Block (STBG) and PROTECT Program grants, and state gas tax.
Contractor
Fisher Industries
Schedule
Below is a general overview of the construction schedule. The schedule is subject to change.
January-June 2024 (Complete):
- Earthwork and widening SB I-15 from St. Rose Pkwy. to Sloan Rd.
- Earthwork and widening both SB and NB I-15 from St. Rose Pkwy. to Silverado Ranch Blvd.
- Earthwork and widening SB I-15 from St. Rose
- Concrete grinding at the Sloan Rd. interchange
- Drainage and electrical improvements
- Bridge resurfacing at Blue Diamond Rd.
- Begin forming sound walls
July-December 2024:
- Earthwork and widening NB I-15 from Sloan Rd. to St. Rose Pkwy.
- Drainage and electrical improvements
- Forming sound walls
- Installing overhead signs
- Rock landscaping
- Fence and guard rail installation
January-June 2025:
- Earthwork and widening NB I-15 from Cactus Ave. to Silverado Ranch Blvd.
- Earthwork and widening SB Blue Diamond Rd to Silverado Ranch Blvd.
- Drainage and electrical improvements
- Forming sound walls
- Rock landscaping
- Fence and guard rail installation
- Installing overhead signs
July-December 2025:
- Mill and fill existing asphalt NB and SB from Warm Springs Rd. to Sloan Rd.
- Electrical improvements
- Rock landscaping
- Fence and guard rail installation
Traffic Control
Project working hours are nightly, Sunday nights starting at 8 p.m. through Friday evenings at 5 p.m.
- Drivers can expect lane shifts and lane reductions to occur with a reduced speed of 55 MPH.
- During daytime hours, Monday-Friday from 5 a.m. to 8 p.m., three lanes of traffic will be maintained in each direction.
- Traffic will be reduced to one lane of traffic in each direction nightly, Sunday-Friday 8 p.m. to 5 a.m.
Project Background
In 2008, an Environmental Assessment (EA) was prepared for the I-15 South Corridor Improvement Project, addressing the environmental effects of improvements along the I-15 corridor, including a portion of Las Vegas Boulevard South, between Sloan Road and Tropicana Avenue. A Finding of No Significant Impact (FONSI) for the overall project was approved by the Federal Highway Administration on April 20, 2009.
In 2022, a reevaluation of the I-15 South EA and FONSI was done to consider changing conditions and new issues that have transpired over the last several years within the I-15 South project area. The reevaluation of effects of the Phase 2 improvements was approved by FHWA and the project immediately moved forward into design. Design plans were finalized in the summer of 2023.
I-15 South Corridor Improvement Project EA_2008
Public Meeting Presentation_November 2022
Contact
NDOT Project Manager: Mauricio Cardenas, P.E.
mcardenas@dot.nv.gov
(702) 671-8876
NDOT Acting Resident Engineer: Shawn Meagher
shawn.meagher@constructnv.com
(702) 481-2362
For noise complaints, please contact Kevin Van Riel with Fisher Industries at (702) 219-3375 or kvanriel@fisherind.com.